Saturday, August 3, 2013

ROAD MILLING IN KENSINGTON, AUGUST 5TH TO 8TH

Kensington Road Milling Schedule
Monday, August 5th, to Thursday, August 8th

Monday, August 5th:
Cortelyou Road, from Coney Island Avenue to Dahill Road
Milling Contractor

Tuesday, August 6th
Cortelyou Road, from Coney Island Avenue to Dahill Road
Milling Contractor


Wednesday, August 7th
Ditmas Avenue, from 40th Street/Dahill Road to Ocean Parkway
Milling Contractor

Thursday, August 8th
Ditmas Avenue, from 40th Street/Dahill Road to Ocean Parkway
 


About three weeks from those dates, paving will begin.

Milling is the noisy process of grinding off the top layer of asphalt or surface of a roadway in preparation for paving.

The night before a street is scheduled to be milled or paved, the Department of Transportation is supposed to post tow-away/no parking signs on both sides of that street. Notice is also posted on the Department of Transportation's Brooklyn Milling and Paving Schedule

The milling and paving schedules can change if the weather or an emergency prevent work from being done. To find out about any changes in the schedule, call 311 from Monday to Friday, 7:00 a.m. to 7:00 p.m.