Other Pages on This Blog

Pages

Monday, August 8, 2016

ROAD PAVING THIS WEEK IN KENSINGTON, WINDSOR TERRACE, AND PROSPECT PARK SOUTH


Road Paving Schedule for 
Kensington, Windsor Terrace,
and Prospect Park South
Monday, August 8th, through Friday, August 12th

Monday, August 8th
 
  • 2 paving crews on McDonald Ave., from 10th Ave. to Fort Hamilton Parkway, at night


Tuesday, August 9th
  • 2 paving crews on McDonald Ave., from 10th Ave. to Fort Hamilton Parkway, at night

Wednesday, August 10th
  • 2 paving crews on 18th Ave., from Coney Island Ave. to Ocean Parkway 
  • 2 paving crews on McDonald Ave., from 10th Ave. to Fort Hamilton Parkway, at night
  • 2 paving crews on Fort Hamilton Parkway, from Ocean Parkway to McDonald Ave., at night

Thursday, August 11th
  • 2 paving crews on 18th Ave., from Coney Island Ave. to Ocean Parkway 
  • 2 paving crews on Coney Island Ave., from Caton Ave. to Cortelyou Road, at night

Friday, August 12th
  • 2 paving crews on Coney Island Ave., from Caton Ave. to Cortelyou Road, at night

The night before a street is scheduled to be paved, the Department of Transportation is supposed to post tow-away/no parking signs on both sides of the street. Notice is also posted on the Department of Transportation's Brooklyn Milling and Paving Schedule. 

Milling and paving schedules can change if either the weather or an emergency prevent work from being done. To find out about any changes in the schedule, call 311 from Monday to Friday, 7:00 a.m. to 7:00 p.m.